Opening and Closing Ceremony of the 19th Asian GamesPower supply service for opening and closing ceremonies ofAsian Paralympic Games (2023)
Construction Period:
150 Days
Equipment and Specifications:
Generators
Cummins: 36 sets, each with capacity ranging from 1000KVA to 1500KVA, ensuring robust power generation for the entire system.
Japan DENYO: No units deployed in this project.
Transformers
Schneider: 12 sets with a total capacity of 6300KVA, forming the backbone of the power transformation system.
ABB: No units utilized for this project phase (400KVA–800KVA).
Distribution Cabinets
Installed 280 sets of power distribution cabinets featuring Schneider components rated between 250A and 2500A for efficient and safe power management.
Cabling
Deployed 350,000 meters of premium Prysmian cables (specifications 70-240 square mm) to support extensive power transmission across the infrastructure.
UPS Systems
Provided 50 sets of Eaton UPS units with a total capacity of 12,000KVA, ensuring continuous, stable backup power throughout the project.
Project Highlights:
Massive Scale: Handling a large quantity of generators and distribution cabinets required meticulous planning and robust execution.
Trusted Brands: Collaborating with industry leaders like Cummins, Schneider, Prysmian, ABB, and Eaton ensured top-quality, reliable equipment.
Power Transformation Focus: The key feature of this project was its large-scale transformer deployment, a critical component for voltage regulation and power supply stability.
Efficient Timeline: Despite the project’s complexity and scale, all tasks were completed within the 150-day construction period, affirming our efficient project management capabilities.