Opening and Closing Ceremony of the 14th National Games andParalympic Games Power Guarantee Lease Service Project (2021)

Project Duration:

  • 90 Days

Equipment Supplied and Specifications:

  1. Generators
    Our project utilized top-tier generators to provide robust power output, including:
    • Cummins generators: 12 units with capacities ranging from 1000KVA to 1500KVA for demanding power requirements.
    • Japan DENYO generators: 6 units with capacities between 600KVA and 800KVA, providing versatile and efficient energy solutions.
  2. Transformers
    To support comprehensive power distribution, we deployed:
    • Schneider transformers (1000KVA–2000KVA): 8 sets designed for high-capacity electrical loads.
    • Schneider transformers (400KVA–800KVA): No units used in this project phase.
  3. Distribution Cabinets
    The system included 280 distribution cabinets fitted with Schneider components (rated 250A–2500A), ensuring safe and effective power distribution across all facilities.
  4. Cabling
    We installed 140,000 meters of high-quality Prysmian cables (specifications 70–240 square mm) to facilitate efficient power transmission with minimal losses.
  5. UPS (Uninterruptible Power Supply)
    For critical backup power, we provided 30 sets of Eaton UPS systems with a combined capacity of 7000KVA, guaranteeing consistent stability and protection against power interruptions.

Project Highlights and Impact:

  • Robust Infrastructure: The deployment of industry-leading brands like Cummins, Schneider, Prysmian, and Eaton ensured a highly reliable power system built to withstand heavy operational demands.
  • Seamless Coordination: Effective integration of generators, transformers, distribution cabinets, and UPS systems enabled stable and continuous power throughout the project lifecycle.
  • Quality and Efficiency: Selecting premium equipment and adhering to strict installation standards minimized downtime and enhanced operational efficiency.
  • Timely Delivery: The full project was completed successfully within the planned 90-day construction period, showcasing our commitment to meeting tight schedules without compromising quality.